Where your budgets come from

Every project figure that reads 'of 600h planned' or 'No budget set' comes from somewhere. See where the fee, the hours and the cost budget on a stage are worked out.

What you'll achieve

Know which numbers a stage's hours, cost and fee figures are worked out from, so you can change the right thing when one looks wrong.

You'll end up with: You can name the source of each budget figure on a stage and fix it in the place it lives.

Before you start

A stage on the project page shows figures such as of 600h planned, Planned cost 50% and A$120,000 fee. Nobody types most of these into the project page. Each one is worked out from something you set elsewhere. This page says where.

Monument keeps three budgets for a stage. They are the fee, the hours and the cost. Each has its own source.

The fee comes from the stage's revenue items

A stage's fee is the total of its revenue items, plus the revenue items of every task under it. A project's fee is the same total for the whole project. Rows that only add up their children are left out, so nothing counts twice.

That is why you never type a fee on the Progress page. You build it on the stage, as revenue items: a fixed fee, a fee from resourcing, a formula or the others. Change the items and the fee changes everywhere.

If a stage has no fee, the figures that divide by the fee (Fee spent, Planned cost and Invoiced) have nothing to divide by. They show no percentage rather than 0%.

The hours come from the schedule, unless there is a target

The hours budget on a stage is one of two numbers.

  • Planned hours. The hours of every allocation on the stage and the tasks under it. These come from the people and roles you booked on the Schedule.
  • An hours target. If the stage, or any task under it, has an hours target, the budget is that target instead. A target is the stage's own target plus the targets of the tasks under it, each counted once. A task under it with no target adds nothing. A target can be a fixed number or a formula, and a formula re-works itself when its inputs change.

Which one you see depends on your access. If you may view or edit the hours target, the budget is the target. If you may not, the budget is the planned hours, as if the target did not exist. The words on the screen read planned in both cases, so check the hours target on the stage when a figure does not match the schedule.

Work complete is the hours logged divided by this budget. With no hours budget, there is nothing to divide by and Work complete stays blank.

The expected by today figure is how much of the budget the stage's allocations say should be done by today. When the stage has no allocations it is a straight line between the stage's start and end dates. A finished stage has no expected figure.

The cost budget comes from planned expenses

Planned cost is the stage's planned expenses divided by its fee. The planned expenses are:

  • the stage's expense items (fixed, recurring or formula), and
  • the booked hours at their cost rates.

Booked team time counts once, from the bookings. A From allocations expense item is left out of the sum so the hours are not counted twice. See rates and rate history.

Fee spent is the other side of this. It is what the stage has cost so far (logged time at cost plus recorded expenses) divided by the fee.

A worked example

Concept Design on Riverside Apartments for the City of Hawthorn.

FigureWhere it comes fromValue
FeeOne fixed-fee revenue itemA$120,000
Planned hoursSarah Chen and Priya Sharma are booked for 600h in total600h
Hours targetNone setnot used
Planned expenses600h at an average cost rate of A$90, plus a A$6,000 Structural Engineer itemA$60,000
Planned costA$60,000 ÷ A$120,00050%
Hours logged so farTime entries on the stage300h
Work complete300h ÷ 600h50%

The stage reads of 600h planned. Now Sarah adds an hours target of 500h to the stage. A person with access to the hours target sees 300h of 500h planned and Work complete becomes 60%. A person without that access still sees 600h and 50%. Nothing was logged differently. Only the denominator changed.

Why a stage says "No budget set"

On the Progress page each stage shows one line under its name. It picks the first of these that applies:

  1. Closed: no new time or invoices, if the stage is closed.
  2. Spending ahead of progress, if it is flagged.
  3. Not started, if nothing is spent and no work is complete.
  4. The fee, for example A$120,000 fee.
  5. The planned hours, for example 600h planned.
  6. No budget set.

So No budget set means the stage has no fee and no planned hours and no hours target. Give the stage a revenue item, or book people on it, and the line changes.

The word no hours planned next to a figure means Monument has no hours budget to show you for that stage.

Troubleshooting

  • Planned cost shows nothing. The stage has no fee. Planned cost is a share of the fee.
  • The hours look different to a colleague's. One of you can see the hours target and the other cannot. See above.
  • A stage with no allocations has hours. A target on the stage or on a task under it supplies the budget.

Where this fits next

For the cost side in detail, see budgeting project costs. For how revenue and expense lists fit together, see how Monument models finance.