Browse articles
- Practice details
- Brand your documents: logo, fonts, colours and artwork
- Project numbering
- Custom fields
- Task statuses
- Task types
- Adding an office
- Office billing details
- Give your people a home entity
- How permissions work
- Setting someone's access level
- Practice finances access
- Rates access
- Access to one project
- Project role access
- Project admin access
- Team role access
- What each access switch controls
- Contacts access
- Project creation access
- Expense claims access
- Report access
- Staff management access
- Sign-in security
- Verify your sending domain
- Activity and undo
- Connect your own AI agent
- Moving and linking stages
- Critical path and automatic dates
- Large projects
- How do I move a task to another stage?
- Billing milestones
- Checklists and notes
- Your projects
- Tracking schedule slips
- How do I change a project's status?
- How do I rename a project?
- Closing a project
- How do I archive or complete a project?
When someone's hours change
Change a team member's working hours from a date, and see on the Team schedule where their booked work no longer fits.
What you'll achieve
Change a booked team member's working hours and find the weeks where their work no longer fits.
You'll end up with: A new schedule from today, and a red lane that shows which booked work to move.
Before you start
A person's working hours are the capacity line every booking is measured against. Change the hours and the bookings stay where they are: the work still needs the same hours, but there is less room for it. The Team schedule shows the weeks where it no longer fits in red.
At Northlight Architects, Priya Sharma works Monday to Friday and is booked for a full week of Concept Design on Riverside Apartments, 40 hours. From today she works Monday to Thursday.
A schedule change starts on a date
Working hours keep a history. Change schedule adds a new version that applies from the day it starts, today unless you pick another day. Earlier days keep the schedule they had, so past timesheets and utilisation stay as they were. If you pick a start before today, the dialog warns you that hours already worked will be recalculated.
- 1
Open Team, then Priya Sharma's page, and choose Working hours on her Profile.
- 2
Click Change schedule. Starts shows today.
- 3
Untick Friday. Her week drops from 40h to 32h.
- 4
Click Save. The new version joins her Version history.
See where the work no longer fits
- 1
Open Schedules, then Team schedule.
- 2
Find Priya's lane in the booked week. It is red: the 40 hours she is booked for now meet 32 hours of capacity.
- 3
Hover over her lane to see the week's allocated hours, her available hours and how many days are over capacity.
The red lane is a prompt, not an error. Move part of the booking to another week or to someone else on the Team schedule.
Troubleshooting
- The lane is not red. The changed days carry no booking, or the booking still fits the shorter week. Check the week that holds the work.
- Past weeks changed too. The new schedule starts before today. Edit the version in Version history and set Starts to the day the change really began.
- The change should only last a few weeks. Add a second change from the day the old hours come back.
Where this fits next
Next, balance capacity in the swimlanes to move the work that no longer fits.